Eastern Foundry Lead – Sandringham Estate, Sandringham

Eastern Foundry Lead – Sandringham Estate, Sandringham

Apr 19, '25

CJB Scaffolding was appointed to deliver a temporary roof system and full access scaffold to a wing of the prestigious Sandringham Estate in Norfolk. The project, carried out on behalf of Eastern Foundry Lead (EFL), involved creating safe access to three sides of the property for the replacement of lead roofing. As a high-profile heritage site, the project required security vetting and clearance before works could begin, ensuring full compliance with estate protocols.

 

Project Overview

This specialist scaffolding project required a carefully coordinated solution to protect a sensitive and historically significant area of the Sandringham Estate. CJB Scaffolding erected a buttressed access scaffold system to three elevations of the wing, providing safe working access for the lead replacement team.

A temporary roof was craned into position over the structure to ensure full weather protection during the works. The use of Monoflex sheeting further enhanced the enclosure, offering protection from the elements while containing any debris during construction activity.

Due to the site’s royal significance, strict pre-works security checks were required and coordinated with estate representatives to permit access and ensure compliance with security protocols.

Scope of Works

  • Full scaffold design and planning tailored to heritage site standards

  • Buttressed access scaffold to three elevations of the property

  • Craned-in temporary roof to protect internal roof spaces

  • Use of Monoflex sheeting for debris and weather protection

  • Ongoing scaffold inspections to ensure compliance and integrity

  • Security coordination and clearance procedures prior to site access

 

Key Challenges & Solutions

  • High-profile site required security protocols and prior clearances

  • Craning in temporary roof required close coordination and precision

  • Scaffold had to be non-invasive and sympathetic to the historic structure

  • Full weatherproofing required to protect the interior from exposure

 

Results & Achievements

  • Enabled full roof replacement with uninterrupted weather protection

  • Delivered a safe, secure, and non-invasive scaffold solution for a heritage environment

  • Maintained estate safety and security standards throughout the project

  • Achieved full compliance while supporting specialist conservation work

Commercial Scaffolding

Latest Projects

Gipping Construction – Muntons Maltings, Stowmarket

Read

Gipping Construction – Ipswich Museum

Read

BMA – Oasis Tower, Gt Yarmouth

Read

Zeno Construction – Kettering Park Tower

Read

Pentaco – Hethersett Academy

Read

Masonic Lodge, Halesworth

Read

Scaffolding Association Certificate
Constructionline Logo
NASC Certificate